The project involves the erection of a 550 TPH CFBC boiler with Thermax make, along with ESP installation for Units I & II. Unit I's foundation is handed over, with manpower and equipment mobilised and progression on critical components. Unit II's foundation handover is ongoing with mobilisation underway. Next steps include road completion, material deliveries, crane mobilisation, and coordination for meeting milestones on time, ensuring smooth workflow.